Sany uses new tech on concrete pour for US$7bn Shiziyang Bridge

Four Sany pump trucks finished pouring the final layer of concrete for the right bearing platform for China鈥檚 Shiziyang Bridge鈥檚 east tower, which will be the world鈥檚 largest double-deck suspension bridge once complete.

Shiziyang Bridge render (Image: Knight Architects) Render of the Shiziyang Bridge double-decker and Warren truss over the Pearl River Estuary in China. (Image: Knight Architects)

The crews used C45 high-strength concrete to pour a total volume of 25,000m3 (32,699 cubic yards) between two circular structures measuring 40m (131ft) in diameter and 9m (30ft) tall.

The four Sany pump trumps worked 22-hours straight on the pour.

Sany, a China-based multinational heavy equipment manufacturer, said a stepless pressure-pumping system and digital main-valve technology improved direction changes by 20% and enabled pumping an additional load of material every hour. The company said the system prevents pipe blockages and promotes energy-saving operations.

The company also said a 鈥榥ew power transmission鈥 system lowered the operating speed of the machines, leading to cost savings, but did not specify the power technology used.

Sany reveals sales from electric- and hydrogen-powered machines Chinese construction equipment manufacturer Sany has revealed the total revenue it generated from both electrically powered and hydrogen-powered machines in 2023
Details for the Shiziyang Bridge in Southeast China

The massive Shiziyang Bridge will have a total length more than 35km (22 miles), and upon completion, will connect the east and west banks of the Pearl River Estuary in China鈥檚 Guangdong-Hong Kong-Macao Greater Bay Area. It will have a 2.2km (1.4 mile) long double-deck suspension at its centre.

UK-based Knight Architects, working with Danish engineering consultant Cowi, delivered the concept design for the bridge.

鈥淭he design has a suspension main span, supported from 367m tall A-shaped towers, and shorter side spans over frame-shaped piers,鈥 explained Knight Architects. 鈥淭he double deck carries a total of 16 lanes. In the main span the decks are the top and bottom chord of a Warren truss.

鈥淭he aim of the proposed bridge is to, within the complex engineering constraints and making functionality, structure, and architecture indissoluble, become both a landmark and a fitting addition to the site, and an important part of the future identity of the area.鈥

It鈥檚 expected to cost just less than US$7 billion to construct and open to traffic in 2028.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Catrin Jones Deputy Editor, Editorial, UK 鈥 Wadhurst Tel: +44 (0) 791 2298 133 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA