Megaprojects: Two reasons why they go wrong (and four key ingredients for success)

A digital render of the high-speed rail line in California, US (Image: SENER)

As a construction project gets bigger, so do the stakes.

A whole host of factors can contrive to send work over time and over budget, with serious consequences for all involved.

In a worst case scenario contractors and clients can end up in legal disputes, there鈥檚 the risk of reputational damage, and projects can end up downscaled and even cancelled. Megaprojects (typically costing $1 billion or more) can find themselves subject to a whole new level of scrutiny.

And yet even when clients and their delivery teams are aware of the risks, things can and still do go wrong.

Portrait image of Prof. Bent Flyvbjerg Bent Flyvbjerg (Image supplied)

Two of the most recent high-profile examples happen to be high-speed rail projects.

In the US, the cost of California鈥檚 high-speed rail system, expected to run 500 miles from Los Angeles to San Francisco, has , up from last year鈥檚 estimate of $105 billion and faces a funding shortfall.

The first phase of the project, will run 171 miles from Merced to Bakersfield but the schedule even for that section has slipped from a solid completion date of 2030, to a window between 2030-33.

Meanwhile in the UK, the High Speed 2 line is now estimated to cost just over 鈧80 billion (US$87 billion) 鈥 a significant hike from the estimate of 鈧62.9 billion (S68.4 billion) in 2015. The government there has delayed the phase 2a of the project due to rising costs and the planned London terminus at Euston also faces delays and uncertainty, despite 鈧332 million (US361.2 million) already being spent on the station鈥檚 design.

Given those projects鈥 troubles and their scale, scope and relative complexity, it鈥檚 tempting to suggest that high-speed rail is particularly prone to schedule and budget overruns.

But according to Bent Flyvbjerg, first BT professor at Oxford University and VKR professor at the IT University of Copenhagen, high-speed rail ranks somewhere in the middle in terms of megaprojects鈥 propensity to encounter such overruns.

Prof. Flyvberg claims to be the most cited scholar in the world on the subject of megaprojects and has written books on the subject, including .

He and his colleagues have built up a database of 16,000 projects around the world to try to understand the differences between success and failure to inform the better management of megaprojects.

In his latest book, Flyvbjerg examines more than 20 different project types and finds that nuclear power projects, putting on the Olympics, and the construction of hydroelectric dams rank among some of the most problematic.

On the other end of the scale, roads projects tend to result in smaller cost overruns and delays, as do wind and solar projects where there is a high level of repeatability.

Two root causes of project failure

Regardless of project type, however, Flyvbjerg sees some common causes at the root of megaproject failures.

And rather than complex engineering challenges, difficult geotechnical conditions or unexpected archaeological finds, it鈥檚 two decidedly human factors that he identifies. He labels them simply as: 鈥榩sychology鈥 and 鈥榩ower鈥.

Ongoing tunnel construction work on the UK鈥檚 High-Speed 2 rail network. Photo: HS2

鈥淲hat surprised us at the beginning of our research is that we expected to find very different reasons for different kinds of projects. But it turns out that the reasons are the same, even for projects that are completely different,鈥 says Flyvbjerg.

Taking psychology first, he explains, 鈥淲e are born with loads of biases 鈥 that is very well documented in behavioural science. For instance, we are born optimists and that鈥檚 a good thing in evolutionary terms. But optimism can be misplaced.鈥

To illustrate his point, he conjures the example of being a passenger on an aeroplane and hearing the first pilot remark to the co-pilot, 鈥淚鈥檓 optimistic about the fuel situation.鈥

鈥淭hat鈥檚 a very clear example of misplaced optimism,鈥 he says. 鈥淎nd what is the fuel of a project? It鈥檚 the budget. Very often, the people who are planning the budget are optimistic about the fuel situation 鈥 which is to say they are being optimistic about the budget. It happens time and again and if you are overly optimistic, you have a cost overrun. If you are optimistic about the schedule, you are going to have a schedule overrun.鈥

It鈥檚 as a result of this that Flyvbjerg and his colleagues have developed a methodology for 鈥渄e-biasing鈥 business plans for projects. 鈥淭here鈥檚 a whole range of well-documented psychological cognitive biases that can trip up and will trip up a project if you are not aware of them and you don鈥檛 have a methodology to deal with them,鈥 he warns.

The second root cause 鈥 what Flyvbjerg calls 鈥減ower鈥 鈥 is deliberate rather than unintentional. 鈥淚t is called 鈥榗ooking the books鈥 in good old American English. If we wanted to get a project approved and get funding, we鈥檇 make it look good on paper. Any idiot can make a project look good on paper. You take the cost and the schedule and you underestimate, you take the benefits and you overestimate.

Want to see more construction insights?

鈥淢ost projects are competing for resources. They get put in a pile and prioritised. And if you want to influence the outcome, it鈥檚 a beauty contest. But on the psychological side, the more beautiful you make yourself on paper, the worse the cost overrun and the worse schedule overrun you could end up with. This is exactly what we see in our data.鈥

Flyvbjerg doesn鈥檛 dismiss other reasons cited for project cost and schedule overruns but sees them as a symptom of other problems, rather than the cause itself. 鈥淧eople will say: 鈥極ur project went wrong because when we were building this high-speed rail line, we had to tunnel through a mountain and when we started drilling we realised the rock was completely different to what we thought it was鈥.

鈥淚t鈥檚 not that these causes don鈥檛 exist 鈥 they are very real. But they aren鈥檛 the real cause. How many times have we done this before and been surprised about what we found in the ground? The problem is that we were optimistic about what we would find. We didn鈥檛 use the empirical data that told us what the risk really was 鈥 and we come back to psychology, namely optimism. So even if the immediate cause looks like it鈥檚 archaeology or geology, it isn鈥檛: It鈥檚 us being optimistic about those things instead.鈥

4 key ingredients for success

Fortunately, there are also notable success stories when it comes to megaprojects Flyvbjerg cites two particular examples: Heathrow Airport鈥檚 拢4.3 billion (US$5.4 billion) Terminal 5 in the UK, which came in on time and on budget and $89 million Guggenheim Museum Bilbao in Spain, built on time and on budget by Ferrovial.

Flyvbjerg and his team have studied both projects in detail and offers four key ingredients crucial to a successful megaproject. They are:

1) Repeatability

Given his Danish roots, it鈥檚 perhaps unsurprising for Flyvbjerg to reach for the analogy of Lego when explaining the benefits of repeatability. 鈥淚f you can build a big project from basic building blocks, then you鈥檒l be ok,鈥 he says. He cites the example of wind farms, where each turbine is made up of several easily repeatable elements. 鈥淏ecause it is repeatable, there is a huge accumulation of learning and people get better and better. Contrast that with nuclear power plants. Even though they鈥檝e tried to make it more modular, they haven鈥檛 succeeded yet. It鈥檚 mostly bespoke and built on location. It takes a long time.鈥

2) A competent, unbiased delivery team

As he previously mentioned, Flyvbjerg stresses the need to remain genuinely unbiased during a project. 鈥淚f you are a good project leader then you de-bias everything you do and you keep people on their toes regarding not falling into that trap,鈥 he says.

red crane lifting a big dome A Sany crane lifting the dome for a nuclear reactor in a single piece

But just as important is a competent delivery team. 鈥淵ou don鈥檛 want someone who has never tried to build the project before. That sounds almost idiotic to say. Who would ever think of letting someone do a project they hadn鈥檛 done before? But you would be surprised.

鈥淚 was an expert witness on a hydroelectric dam project that went terribly wrong. It turned out that the client had hired people from the oil and gas sector to build it because they couldn鈥檛 get anyone from hydroelectric. They assumed that if you are good at building one type of project, you are good at building another and that proved to be a big mistake. You need a delivery team with a good track record.鈥

3) The right incentives

He also recommends setting the right incentive system in place, with both stick and carrot. 鈥淯nfortunately there鈥檚 a tendency to have more stick than carrot and that is not a good idea.鈥

4) Build in innovation and learning

Because megaprojects generally take a long time to build, Flyvbjerg recommends building in the opportunity to make improvements during the delivery process. 鈥淏ecause they have so many different moving parts, it鈥檚 really important to have a design where you can improve things as you go along,鈥 he says.

鈥淭he lifecycle of specific technologies gets shorter and shorter and many technologies don鈥檛 have a lifetime of more than two or three years but delivering a megaproject can often take 10 years or more. So you have to build in the capability to deal with that kind of innovation and even promote it and contribute to it yourself.鈥

Advice for engineers and contractors

As far as members of the delivery team such as consulting engineers and contractors are concerned, they may not have ultimate control over the success of a project. But there are still things they can do to try and influence the outcome, Flyvbjerg asserts.

Perhaps most importantly is to work with an intelligent and understanding client, although he accepts that contractors don鈥檛 often get to choose who they work for.

鈥淲orking with someone you have worked with before has huge advantages for both sides,鈥 he says. 鈥淭hat of course is often very difficult. Only the most experienced clients succeed in having a roster of companies and contractors that they hire in. And from the contractors鈥 side, it鈥檚 even more difficult because they need to work. But that doesn鈥檛 mean that it鈥檚 impossible. And what we find with experienced contractors is that they work with the same clients over and over again. We have examples where this has happened for more than 30 years.鈥

He also calls for better drafting of contracts themselves. 鈥淚t has been a problem for many decades. In the UK, we have many different types of contracts and there is serious work going on to improve them but it鈥檚 difficult and what makes it difficult is risk allocation.

鈥淲ho is going to pick up the risk on projects? Is it going to be the contractor or is it going to be the client, or a mix of the two? The more you can adopt a partnering model, provided that you have experienced contractors and experienced client, the better the results tend to be.

鈥淭he old-fashioned way of thinking that you are allocating all risks to the contractor is a recipe for disaster because it becomes very antagonistic. A lot of energy is spent on deciding and fighting about actually who鈥檚 responsible for things when they go wrong. And there are always things that go wrong in megaprojects.鈥

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Catrin Jones Deputy Editor, Editorial, UK 鈥 Wadhurst Tel: +44 (0) 791 2298 133 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA